Residential Project
Decarbonisation scheme completed at Campus West, Welwyn Garden City on behalf of Welwyn Hatfield Borough Council.
Barrie Beard have also completed various works which include an installation of a new sub main cable & a replacement of the tower plant distribution board.
Barrie Beard Ltd’s scope of work included
This project consisted of power requirements to a new 400A ASHP
A PV Panel Board to accommodate the main building roof & roller city roof PV panels, This has an estimated capacity of 111.6kWp.
Project Data
CLIENT: Welwyn Hatfield Borough Council
COMPLETED: January 2023
Campus West
Share this post: