Aston Villa Football Club, Birmingham
Secondary Power Upgrade Works
Barrie Beard Ltd were involved in the design and installation of a new back-up generator and alterations to the existing LV system to accommodate the essential services.
The installation consisted of a new 1000kVA generator set and associated switchgear. This would then give the stadium a back-up of power supply in the event of a mains failure. Alterations to all relevant circuits were carried out so that they interfaced with the new generator set.
Barrie Beard Ltd’s scope of work included
Stadium control
CCTV systems
Public address and display screen
Radio communications
Security access control
Stand canopy lighting
Exit gate control
Communications systems
Stadium floodlights, 50%
Project Data
CLIENT: Aston Villa Football Club
CONTRACTOR: Hoare Lea
COMPLETED: November 2008
DURATION: 6 Months