Secondary Power Upgrade Works 
Barrie Beard Ltd were involved in the design and installation of a new back-up generator and alterations to the existing LV system to accommodate the essential services. 
 
The installation consisted of a new 1000kVA generator set and associated switchgear. This would then give the stadium a back-up of power supply in the event of a mains failure. Alterations to all relevant circuits were carried out so that they interfaced with the new generator set. 

Barrie Beard Ltd’s scope of work included 

Stadium control 
CCTV systems 
Public address and display screen 
Radio communications 
Security access control 
Stand canopy lighting 
Exit gate control 
Communications systems 
Stadium floodlights, 50% 

Project Data 

CLIENT: Aston Villa Football Club 
CONTRACTOR: Hoare Lea 
COMPLETED: November 2008 
DURATION: 6 Months 
Tagged as: Sports & Leisure