Jordan House, Birmingham
Part of the regeneration programme
Barrie Beard electrical contractors were contracted to assist with the Jordan House, which was completed in March 2022 in conjunction with main building contractor Wates Living Space.
The refurbishment of the block forms part of the regeneration programme by Birmingham City Council, to upgrade main services x 50. The design and installation of new sub-mains to each property. Core drilling works. Installation of heavy gauge cable tray in risers. Design and installation of 2 No main distribution boards. Organising 2 new supplies from WPD, that being the jointing in the road and new cables installed in each switch room.
Barrie Beard Ltd’s scope of work included
Distribution and sub-main installation
Project Data
CLIENT: Birmingham City Council
CONTRACTOR: Wates Living Space
COMPLETED: March 2022
DURATION: 18 Months
Tagged as: Apartments & Residential
Share this post: