Project Overview
Barrie Beard was appointed by Morgan Sindall to deliver the electrical installation for a new three-storey SEN school in Selly Oak, Birmingham.
The new facility comprises classrooms, offices, a ground-floor plant room, roof plant, library and specialist teaching spaces. Barrie Beard delivered a comprehensive electrical installation across the building, including power, lighting, life safety, security, data and renewable energy systems.
Scope of Works
Our works included:
Electrical design and coordination
Main LV switchboard and sub-distribution
Containment and wiring systems
Small power installation
Internal, external and emergency lighting
Lighting control systems
Fire detection and alarm systems
Intruder detection and alarm systems
Access control and CCTV
Structured cabling
Disabled refuge intercom systems
Induction loops
Electrical supplies to mechanical plant
Lightning protection
Earthing and bonding
Solar photovoltaic panel installation
Project Objectives
The key objective was to deliver a high-quality electrical installation within a challenging 22-week programme, ensuring all systems were installed, tested and fully operational in accordance with the client's specification.
The project also provided an opportunity to establish a strong working relationship with Morgan Sindall and demonstrate Barrie Beard's ability to deliver complex electrical projects to the high standards expected by a Tier 1 contractor.
Project Challenges & Delivery
The project was delivered to a demanding programme, requiring close coordination between our installation teams, specialist subcontractors and the wider project team.
Working to Tier 1 standards required detailed technical submissions, extensive coordination and comprehensive O&M documentation. The project also highlighted the importance of early planning and ensuring documentation requirements are considered throughout the project rather than at completion.
The completed project has provided Selly Oak Trust with a modern, fully integrated electrical infrastructure designed to support the specialist requirements of an SEN school, incorporating both robust electrical systems and renewable energy technology.
Project Data
Client: Selly Oak Trust School
Contractor: Morgan Sindall
Completion Date: Sep 2026
Project Duration: 22 Weeks