Barrie Beard Ltd were involved in the design and installation of a new back-up generator and alterations to the existing LV system to accommodate the essential services.
The installation consisted of a new 1000kVA generator set and associated switchgear. This would then give the stadium a back-up of power supply in the event of a mains failure. Alterations to all relevant circuits were carried out so that they interfaced with the new generator set.
Barrie Beard Ltd's scope of work included:
Project Data
Client: Aston Villa Football Club
Main Contractor: Hoare Lea
Contract Duration: 6 months
Services Value: £330,000
Contract Completed: November 2008